Residential on East Las Flores Drive

Drainage plans for a single-family residential fire rebuild following the Eaton Fire.

Drainage plan for Altadena corner lot showing flowline wrapping to Santa Anita Ave with max 5:1 slopes

Location

Altadena

Current Phase

Approved

Project Overview

Single-family residential fire rebuild in Altadena following the Eaton Fire. The 0.1768-acre corner lot drops 10 feet from top of street to rear, requiring careful drainage design across multiple grade transitions. Along the front of the property, we established maximum 5:1 (20%) slopes, then transitioned to a 10-foot-wide 5% slope away from the foundation into a flowline that wraps around each side of the house. This flowline continues to Santa Anita Avenue, where stormwater sheets over the property line above the existing driveway apron and into the street right-of-way.

A new driveway leads to a new garage, with 2.5-foot maximum height walls lifting the driveway enough to maintain 1% minimum sheet flow to the driveway apron and street. Matching into the existing Santa Anita Avenue right-of-way required careful attention to keep the house at a good finished floor elevation while minimizing steps between the house and garage. Keeping slopes at or under 5:1 (20%) meant the project qualified as a drainage plan rather than a full grading plan, simplifying LA County approval. Approved April 2026.

Site Photos

Altadena corner lot with erosion control measures and sandbags prepared for drainage plan installation
Altadena construction site with privacy fence featuring our drainage design for corner lot
Vacant Altadena lot with mature trees before construction with our drainage plan approved
Altadena lot with erosion control wattle and sandbags ready for residential rebuild

Project Progress

October 2025

Initial Assessment

Existing conditions documented. Drainage patterns identified.

October 2025

Submittal

Drainage plans submitted to LA County for review.

April 2026

Approved

Drainage plans approved by LA County.